View of the Transpennine Route Upgrade (TRU) work at Bradley Junction.
The ‘Up Huddersfield’ line has now been laid and is awaiting ballasting.
The crossover between the Down and Up lines has also now been installed, with work ongoing prior to ballasting.
The line between Huddersfield and Heaton Lodge Junction was closed from 2nd May until 25th May to allow track replacement at Bradley Junction and other extensive works around Deighton inconnection with the TRU.